Breaking News :   Fighting COVID-19 in Jammu: Casual approach Irks Central team | Come, live with us: Farooq tells Omar | Month on, probe committee fails to submit report | Bio Diversity Council to act as Govt ‘s Advisor | COVID-19: Recovery rate dips in JK | New Education policy reflects aspirations of everyone: LG Sinha | Police accused of going soft on FIR lodged due to political pressure | “2G Enough For E-Learning”: Centre Defends Throttled Internet In J&K | ‘No restrictions on movement of individuals in J&K’ | Indian Army occupies 6 new heights in Eastern Ladakh | Brijesh Bhau conferred with North India Director Yongmudo | Munish Gupta asks government to solve problems of people of 338 Rampura Nai Basti | BSP demands 27% reservations to SC, ST, OBCs in J&K | JKNPP launches “Rozgar Ka Vaada Poora Karo” campaign | Spiritual Sufi conference after 35 years held at Pulwama | COVID-19: Govt evacuates 4,70,324 stranded JK residents | AP demands infrastructure, conservation plans for Pahalgam | NMC demands inclusion of Punjabi, Gojri as official languages | FAIVM hails Rs 1350 cr financial package | BJP releases State “e-book” on services rendered | Sikh organizations take out protest rally | NDS organises multi-lingual "e- lok sangeet" | 6 gamblers arrested, stake money recovered | 14 years on, Kangoloo-Pachound road yet to get completed | Terrorists build underground bunkers in Shopian to escape Army’s pursuit | 62 kg heroin, two pistols seized as BSF foils infiltration bid along IB | FC Health, Central Team review COVID-19 Control measures in 6 districts | Secularism bedrock of NC, says Omar | Srinagar airport security gets a boost with latest baggage screening system | Accused driver gets bail, Court releases vehicle | NC’s duplicity exposed | DAUGHTERS OF SOIL | Salary Cut- A Welcome Move by the Government | Shiv Sena stages protest against Pakistan | TMF expresses concern over condition of Jammu Hospitals | RSS distributes food packets among needy | Plus Two Forum urges LG to postpone opening of schools | GDC Vijaypur organizes article writing competition | AIVM welcomes financial package | AIBBWA nominates new body with Trilok Motan as national president | International Webinar on Mahatma Gandhi’s thought organized | DSEJ hosts National Webinar on ‘Know Science Simply’ | Free eye check up camp organized | Rana seeks rollback of decision about reopening of schools | KPSS sits on fast unto death against DMRR&R | Tehsildar North distributes 100 domicile certificates at doorsteps | Advisor Bhatnagar visits GMC Jammu | Back Issues  
 
news details
11. 61 KM stretch nearing completion; work on 4.6 KM flyover under Package II in full swing
Jammu-Akhnoor 4-lane project
8/9/2020 1:21:32 AM
Early Times Report

JAMMU, Aug 8: The work on Jammu–Akhnoor Four lane project has gained substantial momentum with the execution of 31 percent work on Package II of the project which starts from 800 meters and ends at 6 km (from canal head to Ganesh Vihar). It includes construction of 4.6 km long flyover.
The flyover will have 126 foundations out of which 93 have been completed. Also the work on package III has gained pace which starts from Ganesh Vihar to Khati Chowk (km 06 to km 26.350).
The Deputy Commissioner, Jammu Sushma Chauhan, visited various construction sites and inspected the pace of progress on the project. ACR Jammu, Vijay Sharma, SDM Jammu North, Pawan Kotwal besides officers from PHE, PDD, NHIDC and other concerned departments also accompanied the Deputy Commissioner.
The senior functionaries of executing agency (NHIDCL Engineers) briefed the Deputy Commissioner Jammu about the work done so far.
The Deputy Commissioner was further informed by the Site Engineer that clearance of structures is complete with all the 580 structures having been cleared in last one year.
It was further told that over 90% land/structure compensation has been disbursed to the rightful claimants.
Giving further details, the DC was told that a total 11.618 km hindrance free stretch has been completed in the last one year.
The Shifting of PDD poles and the infrastructure of PHE department coming in the alignment of the project shall be completed in a scheduled manner.
The instructions have been issued by Deputy Commissioner to the concerned officers to adhere with the instructions and get the work completed in a time bound manner. The on spot directions have been issued to General Manager NHIDCL to improve the condition of in use service lanes.
The patch work shall be completed in a week’s time so that the general public may not suffer due to the poor condition of the road.
  Share This News with Your Friends on Social Network  
  Comment on this Story  
 
 
 
Early Times Android App
STOCK UPDATE
  
BSE Sensex
NSE Nifty
 
CRICKET UPDATE
 
 
 
 
 
 
 
 
   
Home About Us Top Stories Local News National News Sports News Opinion Editorial ET Cetra Advertise with Us ET E-paper
 
 
J&K RELATED WEBSITES
J&K Govt. Official website
Jammu Kashmir Tourism
JKTDC
Mata Vaishnodevi Shrine Board
Shri Amarnath Ji Shrine Board
Shri Shiv Khori Shrine Board
UTILITY
Train Enquiry
IRCTC
Matavaishnodevi
BSNL
Jammu Kashmir Bank
State Bank of India
PUBLIC INTEREST
Passport Department
Income Tax Department
JK CAMPA
JK GAD
IT Education
Web Site Design Services
EDUCATION
Jammu University
Jammu University Results
JKBOSE
Kashmir University
IGNOU Jammu Center
SMVDU